Erosion and Sediment Control Tip #50
Alabama’s new 2022 Blue Book contains some changes related
to silt fences. One change is that the silt fence should be designed for
dewatering and potential overtopping. The silt fence at full capacity should
dewater in 4 to 12 hours. An overflow should be included that conveys the peak
discharge for the design event. While there can be several methods to
meet these requirements, one is shown in the picture by inserting an overflow
and dewatering board at the lowest point in the fence.
Also, remember that a silt fence should pond the runoff water
from its small watershed for the design storm event.
Perry L Oakes, PE
Erosion and Sediment Control Program Coordinator
AL Soil and Water Conservation Committee